Create a Rework Batch Order in Dynamics 365 SCM

MB-335 By islever Editorial Last updated

Short answer

BCE Specify the batch number, set the batch order as a rework batch, and reserve the reworked inventory after estimation.

Question

A chemical manufacturing company uses Dynamics 365 Supply Chain Management. A batch of material has a quality issue and must be reworked. You need to create the rework order for production. Which three options must be set? Each correct answer presents part of the solution. NOTE: Each correct selection is worth one point.
  1. Pick the reworked inventory after estimation.
  2. Specify the batch number on the batch order. Correct Answer
  3. Set the batch order as a rework batch. Correct Answer
  4. Set the item as a Formula production type.
  5. Reserve the reworked inventory after estimation. Correct Answer

Key Takeaways

A rework batch order is flagged as a rework batch and tied to the original defective batch number; the reworked inventory must be reserved so it is allocated to the rework.

To create a rework batch order for a quality-issue batch, set the batch order as a rework batch, specify the original batch number on the batch order, and reserve the reworked inventory (after estimation).

Common mistake: Do not set the item as a Formula production type (the original item's production type is unchanged). Note community debate on reserving before vs after estimation, but the exam-aligned answer reserves after estimation.

Expert Analysis

Why the Answer Is Correct

Three settings are required. Specify the original batch number on the batch order so the rework is traced to the defective batch (B). Set the batch order as a rework batch so it is processed as rework (C). Reserve the reworked inventory after estimation so it is allocated to the rework order (E).

Why the Other Options Are Wrong

  • Option A (pick the reworked inventory after estimation) is not a required setup step.
  • Option D (set the item as a Formula production type) is unrelated; the item's production type is not changed for rework.

Community Comment Notes

Community consensus is BCE (100). One discussant cites older documentation stating reserve before estimation, but the exam-aligned answer is BCE.

Official Reference

https://learn.microsoft.com/en-us/dynamicsax-2012/appuser-itpro/create-a-rework-batch-order

This link opens the official vendor documentation in a new tab.

Community Votes

BCE
100%

100% of anonymous learners picked answer BCE. Votes are pick records left by other test-takers — they are not the verified answer.

Discussion 3 contributions

Compiled from public community threads and reader submissions, lightly edited for clarity. Handles and vote tallies are shown as recorded, and comments reflect the views of individual contributors.

From public community threads 3

  1. GiSi1965 👍 4
    To create a rework order for production in Dynamics 365 Supply Chain Management, you’ll need to configure the following options: Specify the batch number on the batch order (B): When creating a rework order, it’s essential to associate it with a specific batch number. This ensures that the rework is tracked accurately and tied to the correct material batch. Set the batch order as a rework batch (C): Designate the batch order explicitly as a rework batch. This classification helps differentiate it from regular production orders and ensures that it follows the appropriate rework processes. Reserve the reworked inventory after estimation (E): Reserve the inventory for the rework process once the estimation is complete. This step ensures that the necessary materials are available and prevents conflicts with other production orders.
  2. Deetss 👍 1
    Should it be "A" instead of "E"? Documentation states: "You must manually reserve this inventory BEFORE you run estimation." https://learn.microsoft.com/en-us/dynamicsax-2012/appuser-itpro/create-a-rework-batch-order
  3. griffin1212 👍 1
    BCE is correct

Reader comments & corrections

No reader corrections yet — spotted an error or have a note? Share it below.

Log in to comment, report an error, or add a note about this question.

← Back to MB-335 Study Guide