Handle a Broken Machine Mid-Production Order in Dynamics 365 SCM
A company uses Dynamics 365 Supply Chain Management. A piece of machinery that is critical to a production order breaks down during a production order. The completed quantities of the production order must be shipped. The remaining quantity on the production order needs to be completed once the machinery is fixed. Negative inventory is not allowed for the items. You need to resolve the production issue. What should you do?
Community Votes
100% of anonymous learners picked answer A. Votes are pick records left by other test-takers — they are not the verified answer.
Community Insight
A production order in Started status cannot be split; the standard resolution is to ship what is already reported as finished and complete the remaining quantity once the machine is repaired.
When a machine breaks during a production order and the completed quantity must ship while the remainder is finished later, ship the quantity that is already reported as finished; you cannot split a started order.
Do not try to split the current production order (not allowed in Started status), and do not cancel and recreate — ship the reported-as-finished quantity and finish the rest later.
Community Discussion (3 comments)
Comments & Corrections
No comments yet — spotted an error or have a note? Share it below.
Expert Analysis
Why the Answer Is Correct
The completed quantities are already reported as finished, so they can be shipped. Because the production order is in Started status it cannot be split; the remaining quantity is finished once the machine is repaired. Shipping the reported-as-finished quantity is the standard resolution.Why the Other Options Are Wrong
- Option B (cancel and recreate) discards already-posted work.
- Option C (split) is not allowed for an order in Started status.
- Option D (end and recreate) is unnecessary and problematic given consumption already posted.