Mirror a Lean Throughput Activity as a Discrete Route in Dynamics 365 SCM
Short answer
D Create a route with runtime 6, process quantity 1, and operation hours/time 0.0167 (1 hour/60 minutes).
Question
Key Takeaways
Throughput ratio 2 doubles the per-quantity runtime (3 x 2 = 6 min for process quantity 1); runtime is in minutes so hours/time must be 0.0167.
To convert the Lean production flow activity into a Discrete route, create a route with runtime 6, process quantity 1, and operation hours/time 0.0167 (1 hour/60 minutes).
Common mistake: Keep hours/time at 0.0167 (not 1), and keep runtime 6 for process quantity 1; inverting runtime and quantity yields the wrong route.
Expert Analysis
Why the Answer Is Correct
As in the related item, the Lean activity's throughput ratio of 2 doubles the runtime to 6 minutes for process quantity 1. Route runtime is in minutes while the operation hours/time field is in hours, so 1 minute = 1/60 = 0.0167 hour. Option D matches exactly.
Why the Other Options Are Wrong
- Option A uses hours/time = 1, treating 6 minutes as 6 hours.
- Option B and Option C use incorrect runtime/process-quantity pairings.
Community Comment Notes
Community consensus is D (100); this is the same lean-to-discrete conversion as the earlier item, presented with different option letters.
Official Reference
https://learn.microsoft.com/en-us/dynamics365/supply-chain/production-control/routes-operations
This link opens the official vendor documentation in a new tab.
Community Votes
100% of anonymous learners picked answer D. Votes are pick records left by other test-takers — they are not the verified answer.
Discussion 3 contributions
Compiled from public community threads and reader submissions, lightly edited for clarity. Handles and vote tallies are shown as recorded, and comments reflect the views of individual contributors.
From public community threads 3
-
Deetss 👍 2 Answered DI believe the answer is "D." Throughput ratio of 2 indicates product consumes two resources, in other words runtime 3min*2=6min for process quantity of 1. Since our runtime is in minutes, the operation hours/time must be 0.0167. https://learn.microsoft.com/en-us/training/modules/set-up-use-discrete-manufacturing-routes/create-operations-relations +throughput ratio link: https://learn.microsoft.com/en-us/dynamics365/supply-chain/production-control/tasks/define-lean-schedule-groups#associate-product
-
CCexamn 👍 2 Answered DSame like #60 and also #138. But in 138 you cant select correct answer????
-
juan1603 👍 1Same Question than Question #60 of Topic 1 with other answer.