Mirror a Lean Throughput Activity as a Discrete Route in Dynamics 365 SCM

Configure resources, routes, and calendars
Answer Correct answer: D — Create a route with runtime 6, process quantity 1, and operation hours/time 0.0167 (1 hour/60 minutes).

You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item. This item has the following Lean setup: • The setup uses a Lean schedule group with a throughput ratio = 2. • The process activity tied to production flow has the following runtime activity times: time = 3 min, per quantity = 1. • The work cell capacity has a model type of Throughput and an average throughput quantity of 60 per a capacity period of standard workday (8 hour day). • The throughput is 10 per hour. You need to set up a Discrete operation to mirror the item’s production flow activity. What should you do?

  1. Create a route with a runtime = 6, a process quantity = 1, and the operation's hours/time = 1.
  2. Create a route with a runtime = 1, a process quantity = 6, and the operation's hours/time = 1.
  3. Create a route with a runtime = 10, a process quantity = 6, and the operation's hours/time = 1.
  4. Create a route with a runtime = 6, a process quantity = 1, and the operation's hours/time = 0.0167 (e.g. 1 hour/ 60 minutes). Correct Answer

Community Votes

D
100%

100% of anonymous learners picked answer D. Votes are pick records left by other test-takers — they are not the verified answer.

Community Insight

Throughput ratio 2 doubles the per-quantity runtime (3 x 2 = 6 min for process quantity 1); runtime is in minutes so hours/time must be 0.0167.

To convert the Lean production flow activity into a Discrete route, create a route with runtime 6, process quantity 1, and operation hours/time 0.0167 (1 hour/60 minutes).

Keep hours/time at 0.0167 (not 1), and keep runtime 6 for process quantity 1; inverting runtime and quantity yields the wrong route.

Community Discussion (3 comments)

CCexamn 👍 2 Selected: D
Same like #60 and also #138. But in 138 you cant select correct answer????
Deetss 👍 2 Selected: D
I believe the answer is "D." Throughput ratio of 2 indicates product consumes two resources, in other words runtime 3min*2=6min for process quantity of 1. Since our runtime is in minutes, the operation hours/time must be 0.0167. https://learn.microsoft.com/en-us/training/modules/set-up-use-discrete-manufacturing-routes/create-operations-relations +throughput ratio link: https://learn.microsoft.com/en-us/dynamics365/supply-chain/production-control/tasks/define-lean-schedule-groups#associate-product
juan1603 👍 1
Same Question than Question #60 of Topic 1 with other answer.

Comments & Corrections

No comments yet — spotted an error or have a note? Share it below.

Log in to comment, report an error, or add a note about this question.

Submitted for moderation before publishing. Keep it helpful and respectful.

Expert Analysis

Why the Answer Is Correct

As in the related item, the Lean activity's throughput ratio of 2 doubles the runtime to 6 minutes for process quantity 1. Route runtime is in minutes while the operation hours/time field is in hours, so 1 minute = 1/60 = 0.0167 hour. Option D matches exactly.

Why the Other Options Are Wrong

  • Option A uses hours/time = 1, treating 6 minutes as 6 hours.
  • Option B and Option C use incorrect runtime/process-quantity pairings.

Community Comment Notes

Community consensus is D (100); this is the same lean-to-discrete conversion as the earlier item, presented with different option letters.