Plan Unplanned Kanban Jobs Two Weeks Early in Dynamics 365 SCM
Short answer
AE Set Automatic planning to Yes and manually schedule each unscheduled job on its due date.
Question
Key Takeaways
Automatic planning = Yes lets the system schedule the jobs, while manual scheduling on the due date places each job at its due date; both achieve planning the jobs ahead of the season.
To plan thousands of unplanned Kanban jobs to be completed before the next season, set the Automatic planning option for each unscheduled job to Yes, and/or manually schedule each unscheduled job on its due date.
Common mistake: Do not set Automatic planning to No (that prevents auto-scheduling), and do not manually schedule forward from the end of the season or to a prior period — those do not align jobs to the due date before the season.
Expert Analysis
Why the Answer Is Correct
Two valid ways meet the goal. Setting Automatic planning = Yes lets the system schedule the unscheduled Kanban jobs, and manually scheduling each unscheduled job on its due date places them at the required date, completing them before the next season.
Why the Other Options Are Wrong
- Option B (manual forward from end of season) and Option C (prior period of next season) misplace the timing.
- Option D (Automatic planning = No) blocks automatic scheduling.
Community Comment Notes
Community votes are split between BE and AE; AE matches 'plan two weeks prior to the next season' via due-date scheduling.
Official Reference
This link opens the official vendor documentation in a new tab.
Community Votes
50% of anonymous learners picked answer BE. Votes are pick records left by other test-takers — they are not the verified answer.
Discussion 3 contributions
Compiled from public community threads and reader submissions, lightly edited for clarity. Handles and vote tallies are shown as recorded, and comments reflect the views of individual contributors.
From public community threads 3
-
Tonheidie 👍 2I think this is incorrect, and B and E are correct. https://learn.microsoft.com/en-us/dynamics365/supply-chain/production-control/lean-manufacturing-kanban-job-scheduling Schedule schedules the selected jobs according to their due date. (This option resembles automatic planning.) Schedule forward from date tries to schedule the selected jobs according to their due date but constrains the result by using the specified earliest start date. since "Previous period moves the selected scheduled jobs to the start or end of the previous period." will not result in ontime items, since you are still in the first month.
-
Deetss 👍 2A - is correct per: https://learn.microsoft.com/en-us/dynamics365/supply-chain/production-control/visual-scheduling-lean-manufacturing#plan-unplanned-jobs E - then seems to be the consensus from below & per: https://learn.microsoft.com/en-us/dynamics365/supply-chain/production-control/lean-manufacturing-kanban-job-scheduling#manual-scheduling
-
LOR_19 👍 3AE - both work with due date