Plan Unplanned Kanban Jobs Two Weeks Early in Dynamics 365 SCM
A customer produces light projection toys for holiday decorations throughout the year. You are in the first month of a season. Production flows take one day to complete. The floor supervisor reports that seasonal production targets will not be met. You review the Kanban schedule board and identify thousands of unplanned jobs. You need to plan the jobs to be completed two weeks prior to the start of the next season. What are two possible ways to achieve this goal? Each correct answer presents a complete solution. NOTE: Each correct selection is worth one point.
Community Votes
50% of anonymous learners picked answer BE. Votes are pick records left by other test-takers — they are not the verified answer.
Community Insight
Automatic planning = Yes lets the system schedule the jobs, while manual scheduling on the due date places each job at its due date; both achieve planning the jobs ahead of the season.
To plan thousands of unplanned Kanban jobs to be completed before the next season, set the Automatic planning option for each unscheduled job to Yes, and/or manually schedule each unscheduled job on its due date.
Do not set Automatic planning to No (that prevents auto-scheduling), and do not manually schedule forward from the end of the season or to a prior period — those do not align jobs to the due date before the season.
Community Discussion (3 comments)
Comments & Corrections
No comments yet — spotted an error or have a note? Share it below.
Expert Analysis
Why the Answer Is Correct
Two valid ways meet the goal. Setting Automatic planning = Yes lets the system schedule the unscheduled Kanban jobs, and manually scheduling each unscheduled job on its due date places them at the required date, completing them before the next season.Why the Other Options Are Wrong
- Option B (manual forward from end of season) and Option C (prior period of next season) misplace the timing.
- Option D (Automatic planning = No) blocks automatic scheduling.