Configure Asset Management for Fuel and Maintenance in Dynamics 365

Configure asset management
Answer Correct answer: B, E — Configure counter types to track fuel usage in liters and create attributes to account for additional maintenance planning time.

A manufacturing company uses Dynamics 365 Supply Chain Management. The company replaced its burners to limit carbon dioxide emissions. The new burners require frequent servicing to be compliant with environmental regulations. The new burners are more complex and take longer to service than the previous burners. The production controller must track fuel use in liters to schedule timely maintenance. The additional time taken to plan maintenance must be considered. You must configure the system to meet the requirements. Which two actions should you perform? Each correct answer presents part of the solution. NOTE: Each correct selection is worth one point.

  1. Register consumption.
  2. Configure counter types. Correct Answer
  3. Set up asset service level.
  4. Configure asset BOM.
  5. Create attributes. Correct Answer

Community Votes

AD
67%
BE
33%

67% of anonymous learners picked answer AD. Votes are pick records left by other test-takers — they are not the verified answer.

Community Insight

The core concept is linking physical asset metrics (fuel liters) to maintenance schedules using counters, while handling complex service requirements through attributes rather than simple BOMs.

This question addresses configuring asset management in Dynamics 365 Supply Chain Management to track fuel consumption and adjust maintenance planning times. The correct solution involves setting up counter types for usage tracking and creating attributes to capture specific maintenance data.

Many candidates select 'Register consumption' and 'Configure asset BOM', likely due to a misunderstanding of how consumption is tracked versus how it is configured, and confusing BOMs with attribute definitions.

Community Discussion (3 comments)

Jeddai 👍 5
Shouldn't it be A and C ?
globeearth 👍 1 Selected: BE
B. Configure counter types - This configures the system to track fuel use in liters (e.g., a “Fuel Consumption” counter) and link it to a maintenance plan (e.g., service every 1,000 liters). It ensures timely maintenance scheduling based on usage, directly meeting the first requirement. E. Create attributes - This configures the system to account for the additional planning time due to the burners’ complexity. An attribute like “Estimated Service Time” (e.g., 4 hours) can be added to the asset and used in planning processes, meeting the second requirement. Why not A and D. A. Register consumption: This is an operational step, not a configuration action. It happens after maintenance, not as a setup for fuel tracking or time planning. D. Configure asset BOM: While useful for defining the burners’ parts and tracking their consumption post-maintenance , it doesn’t directly track fuel use (an operational metric) or address planning time.
Elyse0814 👍 2 Selected: AD
I feel like the answer is correct. Register consumption for the fuel and configure an asset bom to track/account for that consumption. https://learn.microsoft.com/en-us/dynamics365/supply-chain/asset-management/objects/object-bom

Comments & Corrections

No comments yet — spotted an error or have a note? Share it below.

Log in to comment, report an error, or add a note about this question.

Submitted for moderation before publishing. Keep it helpful and respectful.

Expert Analysis

Why the Answer Is Correct

The scenario requires two distinct configurations: tracking fuel use in liters to schedule maintenance and accounting for additional planning time. Configuring counter types allows the system to define 'liters' as a measurable unit linked to an asset, enabling automatic triggers for maintenance based on consumption thresholds. Creating attributes allows you to define custom properties or flags on the asset or maintenance activity, such as 'complexity level' or 'additional time required,' which can then be used in planning rules or simply recorded for compliance.

Why the Other Options Are Wrong

Registering consumption (A) is an action performed during operation, not a configuration step to enable the tracking capability itself; the counter must exist first. Setting up asset service level (C) defines performance metrics like uptime, not the scheduling logic based on fuel volume. Configuring an asset BOM (D) lists the components required for repair but does not inherently track the consumption of fuel to trigger that repair or store the time complexity as a schedulable parameter.

Community Comment Notes

One user argued for AD, stating that registering consumption tracks fuel and the BOM accounts for it, but this conflates the transactional act with the setup requirement. Another user correctly identified BE, noting that counters handle the 'liters' requirement and attributes handle the 'additional time' complexity. A third commenter suggested AC, missing the nuance that service levels are for SLAs, not operational scheduling triggers.

Exam Strategy

Always distinguish between 'configuration' steps (setting up counters, attributes, BOMs) and 'transactional' actions (registering consumption). When a question asks to 'track' something to 'schedule' maintenance, look for Counter Types first. When it mentions 'additional time' or 'complexity' affecting planning, look for Attributes.

Frequently Asked Questions

Why isn't Register Consumption the correct configuration?

Registering consumption is a transactional action taken when fuel is actually used. To 'track' it for scheduling, you must first configure the Counter Type that defines what is being measured.

Can Asset BOM handle the additional planning time requirement?

No. An Asset BOM lists the parts needed for repair. It does not store metadata about the complexity or duration of the service, which is best handled by Attributes.

Related Analysis

← Back to MB-330 Study Guide