Which plan keeps mission-critical services available during an incident?

CS0-003 By islever Editorial Last updated

Explain the incident management life cycle's preparation and post-incident activity phases

Short answer

A A business continuity plan maintains mission-critical services available during an incident, while a disaster recovery plan only restores systems afterward.

Question

Which of the following will most likely ensure that mission-critical services are available in the event of an incident?
  1. Business continuity plan Correct Answer
  2. Vulnerability management plan
  3. Disaster recovery plan
  4. Asset management plan

Key Takeaways

The trap is confusing BCP with DRP; the phrase "available in the event of an incident" demands availability during disruption, not post-incident restoration.

This CS0-003 question tests continuity versus recovery planning: a business continuity plan (A) keeps mission-critical services available while an incident is in progress, whereas a disaster recovery plan restores systems only afterward.

Common mistake: C, the disaster recovery plan, is the most tempting error because it also protects critical services — but DRP is post-incident restoration of IT systems and data, not sustained availability while the incident is ongoing.

Expert Analysis

The qualifier that decides it The stem asks which plan will most likely ensure that mission-critical services are available in the event of an incident. Two words carry the whole question: "available" (service stays up) and "in the event of" (during the disruption, not after it). That is the textbook definition of business continuity — sustaining essential functions while the incident is still unfolding.

Why A is correct Option A, the business continuity plan, identifies essential functions, names the systems and processes that must be sustained, and details how to keep them running — hot sites, redundant staffing, and manual workarounds that are managed 24/7. Community discussion reinforces this reading: the most-endorsed explanation notes the BCP "states the essential functions of the business, identifies which systems and processes must be sustained, and details how to maintain them," and a course-based comment points out that a hot site exists precisely to keep mission-critical services running during an incident.

Why the others fail Option C, the disaster recovery plan, is the strongest distractor and the answer a minority argued for. DRP is restorative: it re-energizes and returns IT systems and data to normal operation after a disaster. It does not guarantee availability while the incident is in progress, so it misses the "available in the event of" wording. Option B, the vulnerability management plan, is preventive — it scans and prioritizes weaknesses and never sustains services during an outage. Option D, the asset management plan, is an inventory and ownership record with no availability procedures at all.

The takeaway Read the temporal cue: continuity = during, recovery = after.

Official Reference

https://www.comptia.org/certifications/cybersecurity-analyst

This link opens the official vendor documentation in a new tab.

Exam Strategy

On plan-selection questions, parse the temporal and outcome cues first: "during" or "available" points to business continuity, "restore" or "recover" points to disaster recovery, and "prevent" or "identify weaknesses" points to vulnerability management. Eliminate options whose scope is a different phase of the incident life cycle, even if they sound security-relevant. When two plans seem equally valid, pick the one whose stated objective matches the exact verb in the stem rather than the broader document.

Frequently Asked Questions

Why is business continuity chosen over disaster recovery here?

Business continuity keeps mission-critical services running while an incident is happening; disaster recovery only re-establishes systems and data after the disruption. The stem's "available in the event of" demands during-incident availability, so BCP wins.

Doesn't a disaster recovery plan also protect critical services?

Yes, but indirectly and later. DRP focuses on restoring IT infrastructure and data post-disaster, whereas BCP is the broader program that sustains essential business functions throughout the incident.

How do vulnerability and asset management plans relate to availability?

A vulnerability management plan prevents and prioritizes flaws before an incident, and an asset management plan records what the organization owns. Neither contains procedures to maintain service availability during a disruption.

More CS0-003 FAQ →

Community Votes

A
65%
C
31%
B
4%

65% of anonymous learners picked answer A. Votes are pick records left by other test-takers — they are not the verified answer.

Discussion 44 contributions

Compiled from public community threads and reader submissions, lightly edited for clarity. Handles and vote tallies are shown as recorded, and comments reflect the views of individual contributors.

From public community threads 30 of 44

  1. attesco 👍 28 Answered A
    The Answer here is A, because a business continuity plan (BCP) is a document that consists of the critical information an organization needs to continue operating during an unplanned event. The BCP states the essential functions of the business, identifies which systems and processes must be sustained, and details how to maintain them. Note that a Disaster recovery plan is a document to re-energise systems or repair a system after it has been affected by a bad incidents
  2. DARKVEGETA 👍 8 Answered A
    I thought the answer C. Disaster recovery plan but I went back to Udemy CYSA+ CSO-003 course and Jason Dion stated in his video under Section 17: Incident Response Preparation, Chapter 139. Business Continuity Plan that a hot site would be used mission-critical things in a event of a incident because they would have to managed 24/7. Correct answer will be A. Business continuity plan.
  3. ms123451 👍 8
    This is incorrect, it is Disaster Recovery Plan, which is how to restore mission critical systems in case of a disaster, a BCP involves everyone and everything during and after a disaster
  4. LoneStarChief 👍 8
    The question makes no mention of a "Disaster" so A is the correct answer.
  5. nmap_king_22 👍 5
    Agreed
Show 25 more comments
  1. BanesTech 👍 4 Answered C
    A disaster recovery plan (DRP) outlines the procedures and protocols to follow in the event of a disaster or disruptive incident that affects the availability of critical systems and services. It typically includes strategies for restoring operations, recovering data, and ensuring the continuity of essential business functions. By having a robust disaster recovery plan in place, organizations can minimize downtime, mitigate the impact of incidents, and ensure the availability of mission-critical services during and after the occurrence of disruptive events. While option (A) Business continuity plan is an essential component of an organization's overall resilience strategy, it does not specifically address the restoration and availability of mission-critical services in the same way that a disaster recovery plan does.
  2. kmordalv 👍 4 Answered A
    The correct answer should be A Business continuity focuses on keeping the business operational during a disaster, while disaster recovery focuses on restoring access to data and IT infrastructure after a disaster. A company's business continuity planning should be the foundation of its disaster planning, so it should precede disaster recovery planning.
  3. alialzehhawi 👍 4
    The Correct answer is A. It says in case of incidents and not disasters.
  4. Japtas 👍 3
    To ensure that mission-critical services are available during and after an incident, a plan that addresses maintaining operations and minimizing disruptions is required. Both Business Continuity Plan (BCP) and Disaster Recovery Plan (DRP) are relevant, but BCP focuses on maintaining ongoing availability, while DRP focuses on post-incident recovery. Correct Answer: A. Business Continuity Plan (BCP) The BCP is most likely to ensure that mission-critical services remain available in the event of an incident, as it is designed to keep essential business operations running under various adverse conditions.
  5. Aderli 👍 3 Answered A
    in the CySA+ study guide says. The goal of the business continuity program is to ensure that the organization is able to maintain normal operations even during an unexpected event. When an incident strikes, business continuity controls may protect the business’ core functions from disruption. The goal of the disaster recovery program is to help the organization quickly recover normal operations if they are disrupted. An incident may cause service disruptions that would trigger the disaster recovery plan.
  6. grelaman 👍 3 Answered C
    While both plans (BCP and DRP) are crucial for ensuring the availability of mission-critical services, the disaster recovery plan is specifically focused on IT system recovery, making it the more immediate and direct solution in the event of IT-related incidents. BCP serves as a more comprehensive strategy that includes DRP as a part of its implementation. So, having a BCP is vital, but the DRP is the answer that directly addresses ensuring availability in IT-related incidents.
  7. throughthefray 👍 3
    What a long explanation just to pick the wrong answer lmao. BCP directly answers the question of keeping systems available, meaning that they are brought back to function as soon as possible (even instantly if possible through the use of redundancy) DRP confronts a scenario of picking up the pieces due to full system wide functionality loss. Answer is A, Broski
  8. Redman69 👍 3
    The answer is A. I just took the ICS2 CC exam and passed. BCP is the choice anytime the words continuity or continuous are used. Disaster Recovery Plan is how you get the critical systems back up and functioning. I also work as a Site Reliability Engineer and maintaining the BCP and DRP are part of my job.
  9. cy_analyst 👍 3 Answered A
    From the official book: The goal of the business continuity program is to ensure that the organization is able to maintain normal operations even during an unexpected event. When an incident strikes, business continuity controls may protect the business' core functions from disruption.
  10. b0ad9e1 👍 3 Answered A
    BC - enables a business continue if there is an incident. DR - enables a business to recovery from a disaster.
  11. kentasmith 👍 3
    This is a good read. https://www.ibm.com/blog/business-continuity-vs-disaster-recovery-plan/
  12. Baz10 👍 3
    Cracking comment, very indepth!
  13. bob33 👍 2
    I The best option to ensure that mission-critical services are available in the event of an incident is: A. Business continuity plan A Business Continuity Plan (BCP) outlines procedures and instructions an organization must follow in the face of disaster, whether fire, flood, or cyberattack. The BCP ensures that essential functions can continue during and after a disaster, helping to maintain mission-critical services.
  14. RobV 👍 2 Answered C
    C. DRP In the context of the question about ensuring mission-critical services, both a Business Continuity Plan and a Disaster Recovery Plan are important. However, when it comes to specifically ensuring the availability of mission-critical services in the event of an incident, a Disaster Recovery Plan is more directly focused on the IT aspects critical for service availability.
  15. Uncle_Lucifer 👍 2 Answered C
    Ignore my previous A selection. This is more CSSP scenario, not CASP. Disaster recovery is the process of maintaining or reestablishing vital infrastructure and systems following a natural or human-induced disaster, such as a storm or battle. It employs policies, tools, and procedures.
  16. Serghey927 👍 2 Answered A
    BCP: why so ? well I tried to remember the videos of Prof Messer, where BCP automatically = COOP in the case of the emergency, take the receipts on paper, answer the phone calls manually and log them. DRP, is more inclided to the effort to remediate the situation.
  17. LiveLaughToasterBath 👍 2 Answered C
    The question refers to MISSION critical instead of business critical ($$$). There could be an internal db server that the company cannot operate without, whereas business critical could refer to an app customers use that make the business $$$.
  18. BAMMRM 👍 2 Answered A
    a business continuity plan (BCP) is a document that consists of the critical information an organization needs to continue operating during an unplanned event.
  19. 499f1a0 👍 2 Answered A
    notice the word incident in the question, it is not disaster so the answer is A which is BCP
  20. johnrambo1stblood 👍 2
    The keyword is "available"; in that case, it is business continuity. A
  21. kmordalv 👍 2 Answered C
    After revising the question, I change the answer to C
  22. Uncle_Lucifer 👍 2 Answered A
    I knew this from CASP CAS-004. BCP all the way!
  23. Uncle_Lucifer 👍 1
    After looking at the definitions, I believe C is the correct answer - DRP. A disaster recovery plan (DRP) is a documented, structured approach that describes how an organization can quickly resume work after an unplanned incident. Disaster recovery is the process of maintaining or reestablishing vital infrastructure and systems following a natural or human-induced disaster, such as a storm or battle. It employs policies, tools, and procedures. A DRP is an essential part of a business continuity plan (BCP). Though BCP contains DRP, the question only applies to DRP
  24. nmap_king_22 👍 1 Answered B
    To ensure that mission-critical services are available in the event of an incident, the most relevant plan is: A. Business continuity plan Explanation: A Business Continuity Plan (BCP) is specifically designed to ensure that critical business processes, including mission-critical services, can continue to operate during and after various types of incidents, such as natural disasters, cyberattacks, or other disruptions. It focuses on maintaining essential functions and minimizing downtime.
  25. ReViive 👍 1
    A. Business Continuity Plan (BCP): While a BCP is crucial for ensuring the continuation of business operations during and after a disaster, it encompasses a broader scope than a DRP. BCPs are designed to keep the entire business running, not just the IT or mission-critical services. Although most voted for in your options, a BCP includes the DRP as part of its framework. The DRP is more specifically targeted at restoring critical IT services, which is why C is a more precise answer.

Reader comments & corrections

No reader corrections yet — spotted an error or have a note? Share it below.

Log in to comment, report an error, or add a note about this question.

← Back to CS0-003 Study Guide