First Step in Organizational Application Update Deployment

220-1202 By islever Editorial Last updated

Given a scenario, apply change management procedures

Short answer

B Submitting request forms initiates the formal change management process required before deploying organizational application updates.

Question

A support specialist must apply a new application update to an entire organization. Which of the following is the first step in this process?
  1. Backup plan
  2. Request forms Correct Answer
  3. Sandbox testing
  4. Peer review

Key Takeaways

The trap is choosing technical steps like testing or backup first; however, administrative authorization via change requests must precede all technical implementation.

This CompTIA A+ question focuses on the change management process for enterprise software updates. The correct initial step is submitting request forms to initiate formal change control procedures.

Common mistake: Candidates often choose 'Sandbox testing' because it is a critical technical step, but it occurs after the change request is approved and scheduled, making it not the *first* step in the overall process.

Expert Analysis

The question asks for the first step in applying a new application update to an entire organization. This scenario falls under IT Service Management (ITSM) and specifically Change Management.

When deploying updates at an organizational scale, you cannot simply install software (Option A is vague/wrong order), test it immediately without approval (Option C is a technical step, not procedural), or rely on informal peer review (Option D is insufficient for enterprise-wide changes). The standard procedure requires initiating a formal Change Request via Request Forms (Option B). This ensures that the change is documented, reviewed for risk, approved by the Change Advisory Board (CAB) if necessary, and scheduled appropriately.

Comments correctly identify that submitting a change request is the primary administrative action before any technical work begins. Without a requested form/record, the deployment violates change management policies, potentially causing unapproved outages or security risks. Therefore, obtaining proper authorization through documentation is the mandatory first step.

Exam Strategy

Always distinguish between administrative/procedural steps and technical steps. In 'Given a scenario' questions involving large-scale changes, look for options related to documentation, approval, or scheduling (like Change Requests) as the first step, rather than immediate technical execution.

Frequently Asked Questions

Why can't I start with sandbox testing?

Testing is a technical validation step that should only occur after the change has been formally requested, reviewed, and approved through the change management process.

What is the purpose of request forms in this context?

Request forms document the proposed change, allowing stakeholders to assess risk, schedule maintenance windows, and authorize the deployment before it happens.

More 220-1202 FAQ →

Community Votes

B
100%

100% of anonymous learners picked answer B. Votes are pick records left by other test-takers — they are not the verified answer.

Discussion 1 contributions

Compiled from public community threads and reader submissions, lightly edited for clarity. Handles and vote tallies are shown as recorded, and comments reflect the views of individual contributors.

From public community threads 1

  1. Damoona 👍 1 Answered B
    Before applying an application update across an organization, the first step is to submit a change request through the organization's change management process.

Reader comments & corrections

No reader corrections yet — spotted an error or have a note? Share it below.

Log in to comment, report an error, or add a note about this question.

Practice All 220-1202 Questions

Access 105 questions with complete answers and detailed explanations.

View Full 220-1202 Practice Test →

← Back to 220-1202 Study Guide